Directions for Questions : These questions are based on the table given below

ADDITIONAL Directions for Questions: For these questions, assume that the cost of the project is incurred in the year of completion. Interest is charged @10% per annum.

CAT/1997

Question . 254

What is the cost incurred (in Rs. crore) for projects completed in 1998?

View Answer

Explanatory Answer

Method of solving this CAT DILR Question from Data Tabulation question

(c) Cost incurred in projects completed in 1998 = Rs 225 + Rs 250 = Rs 475 crore

Total cost including interest = Rs 475 + Rs 47.5 = Rs 522.5