Question . 277

Under the new technique, which stage of Software development is most expensive for Mulayam Software company?

View Answer

Explanatory Answer

Method of solving this CAT DILR Question from Data Tabulation question

(d) Total cost in a stage = ( No. of man months) × ( cost per man month in that stage )

Total cost in specification = (2 + 3)40,000 = Rs 2,00,000

Total cost in design = (4+3+5)20,000 = Rs. 2,40,000

Total cost in coding = Rs 1,40,000 (from previous Q.)

Total cost in testing = (4+1)15000 = Rs. 75000

Hence design is the most expensive stage.