Question . 275
Due to overrun in “Design”, the Design stage took 3 months, i.e. months 3, 4 and 5 . The number of people working on Design in the fifth month was 5. Calculate the percentage change in the cost incurred in the fifth month.(Due to improvement in “Coding” technique, this stage was completed in months 6 - 8 only )