Directions for Questions: These questions are based on the information and two graphs given below.

Figure 1 shows the amount of work distribution , in man - hours for a software company between offshore and onsite activities. Figure 2 shows the estimated and actual work effort involved in the different offshore activities in the same company during the same period. [Note : onsite refers to work performed at the customer’s premise and offshore refers to work performed at the developer’s premise.]

CAT/2001

Question . 107

If the total working hours were 100 which of the following tasks will account for approximately 50 hours?

View Answer

Explanatory Answer

Method of solving this CAT DILR Question from Line Chart & Bar Chart question

(a) Total hours spent = 1170 

Hours in coding = 430 + 100 = 530 = 45.3%

House in Design = 190 = 16.2%

House in Offshore testing = 290 = 24.8%

House in Offshore testing + Design = 290 + 190 = 480 = 41%

Hence (a) is the closest option