CAT DILR Questions | CAT Line Chart & Bar Chart questions

Comprehension

Directions for Questions: These questions are based on the information and two graphs given below.

Figure 1 shows the amount of work distribution , in man - hours for a software company between offshore and onsite activities. Figure 2 shows the estimated and actual work effort involved in the different offshore activities in the same company during the same period. [Note : onsite refers to work performed at the customer’s premise and offshore refers to work performed at the developer’s premise.]

CAT/2001

Question . 104

Which of the work requires as many man- hours as that spent in coding?

View Answer

Explanatory Answer

Method of solving this CAT DILR Question from Line Chart & Bar Chart question

(a) Man hours spent in coding = 430 + 100 = 530

Man hours spent in offshore design and coding = 100 + 430 = 530