CAT Quantitative Ability Questions | CAT TIme, Speed, Distance and Work questions

CAT/2002

Question . 91

6 technicians take total 10 hours to build a new server from Direct Computer, with each working at the same rate. If six technicians start to build the server at 11:00 am, and one technician per hour is added beginning at 5:00 pm, at what time will the server be complete?

View Answer

Explanatory Answer

Method of solving this CAT Quantitative Ability Question from TIme, Speed, Distance and Work question