CAT Quantitative Ability Questions | CAT TIme, Speed, Distance and Work questions
CAT/1998
Question . 125
A company has a job to prepare certain no. of cans and there are three machines A, B & C for this job. A can complete the job in 3 days, B can complete the job in 4 days and C can complete the job in 6 days. How many days the company will take to complete job if all the machines are used simultaneously?
View Answer
Explanatory Answer
Method of solving this CAT Quantitative Ability Question from TIme, Speed, Distance and Work question